K-12 Schools
Filer School District: HSA assisted Filer School District in successfully passing a $16.4 million bond in May 2008. This bond allows for the construction of a new intermediate school, high school extracurricular & community facilities and several maintenance projects. These projects are currently in the design stages and are scheduled to open in Fall 2010.
For further information, please click the links below.
Filer Site Plan
Filer Bond Brochure
Hagerman School District: HSA is currently assisting Hagerman School District in pre-design and bond services for a Elementary school addition.
For further information, please click the links below.
Hagerman Site Plan
Mt. Home School District: In 2007 HSA was commissioned by Mountain Home School District to provide pre-design and bond services for the Mtn. Home Jr. High School conversion.
For further information, please click the links below.
View Rendering of the Mt. Home Jr. High School project.
|

Size: 146,214 S/F
Building COst: $12,224,000
Cost Per S/F: $84 /s/f
Site Development: $1,500,000
Total Project Cost: $13,724,000
Year: 2001
Size: 55,675 SF
Building Cost: $4,198,325
Cost per/SF: $75/SF
Site Development: $200,000
Total Project Cost: $4.4 mil.
Year Completed: 2005
Size: 6000 SF
Building Cost: $410,000
Cost per/SF: $65/SF
Site Development Cost: $90,000
Total Project Cost: $500,000
Year Completed: 1999
Size in SF: 6048
Building Cost: $560,000
Cost per/SF: $92/SF
Site Development Cost: $68,000
Total Project Cost: $628,000
Year Completed: 2000
Addition Size: 17,175SF
Cost per SF: $145/SF
Total Project Cost: 2.5 million
Year Completed: 2005
Size: 39,754 SF
Total Project Cost $3,700,000
Year Completed: 1998
Size: 41,000 SF
Cost per/SF: $36/SF
Total Project Cost: 1.5 million
Year Completed: 2000
Size in SF: 56,000 SF
Building Cost: $4,680,000
Cost per/SF: $83.50/SF
Site Development Cost: $750,000
Total Project Cost: $5,430,000
Year Completed: 2001
Construction Cost: $1,299,800
Size 9419 S/F
Year Completed: 2007
Construction Cost: $1,860,000
Size 11,589 S/F
Year Completed: 2008
|